PIT01 Datacenter Power Maintenance

Scheduled Maintenance Report for RedHelm Cloud

Completed

The scheduled maintenance has been completed.
Posted Jun 20, 2026 - 15:16 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 17, 2026 - 15:16 EDT

Scheduled

The datacenter at our PIT01 location is performing expedited power maintenance over the next few days. They will be performing maintenance on the A-side and B-side power (not at the same time). The RedHelm Cloud equipment is fully redundant so no impact is expected. However, customers that have equipment that does not have redundant power will be impacted by this maintenance.
Posted Jun 17, 2026 - 15:15 EDT
This scheduled maintenance affected: PIT01 (Pittsburgh, PA) (Co-Lo).